With installed capacity to generate 11,233.1 MW of energy and physical guarantee of 4,571 MW on average, the Belo Monte Hydroelectric Complex has 18 Generating Units (UGs) of 611.11 MW each in the Main Powerhouse (Belo Monte HPP), and six UGs of 38.85 MW each in the Complementary Powerhouse (Pimental HPP). Through SIN it supplies energy to the entire country. In terms of installed capacity, it is the fifth largest hydroelectric plant in the world, and the largest 100% national hydroelectric plant. For more information, visit our website: Belo Monte Hydroelectric Complex (norteenergiasa.com.br).
2022 | |||
UNIT | PLANNED SHUTDOWN | NON-PLANNED SHUTDOWN | AVERAGE AVAILABILITY (%) |
Belo Monte | 13,786 | 716 | 90.8 |
Pimental | 1,478 | 166 | 96.9 |
2023 | |||
UNIT | PLANNED SHUTDOWN | NON-PLANNED SHUTDOWN | AVERAGE AVAILABILITY (%) |
Belo Monte | 11,954 | 374 | 99.69 |
Pimental | 1,742 | 181 | 96.34 |